UHV MGMT6355 midterm exam

Question 1

A process flowchart uses symbols to represent which of the following?

Factory location

Warehouse space available

Work force schedules

Flows of material or customers

Data analysis

Question 2

An activity-system map is which of the following?

A network guide to route airlines

A listing of activities that make up a project

A diagram that shows how a company’s strategy is delivered to customers

A facility layout schematic noting what is done where

A timeline displaying major planned events

Question 3

When deciding to add capacity to a factory which of the following need not be considered?

Maintaining system balance

The frequency of capacity additions

Use of external capacity

Immediate product demand

Availability of raw materials

Question 4

Which of the following is a basic type of process structure?

Process flow diagram

Product matrix

Process matrix

Workcenter

Manual assembly

Question 5

If the actual output of a piece of equipment during an hour is 500 units and it’s best operating level is at a rate of 400 units per hour, which of the following is the capacity utilization rate?

0.75

1.00

1.25

1.33

100

Question 6

In a workcenter, machine A has a ten minute set-up time per batch and a two minute per unit run time. Machine B performs the identical function but has a set-up time of thirty minutes and a one minute run time per unit. The workcenter makes products in batches ranging from one unit to one hundred units. Assuming capacity is not a limitation on either machine, on which batches should machine B be used?

All batches should be run on machine B

Batches of more than 20 units should be run on machine B

Batches of fewer than 80 units should be run on machine B

Batches with up to 50 units should be run on machine B

No batches should be run on machine B

Question 7

If all you knew about a production system was that total daily output was 400 units and the total labor necessary to produce the 400 units was 350 hours, what kind of productivity measure could you use to compute productivity?

Partial measure

Multifactor measure

Total measure

Global measure

All of the above

Question 8

Capacity planning involving acquisition or disposal of fixed assets such as buildings, equipment or facilities is considered as which one of the following planning horizons?

Intermediate-range

Long-range

Short-range

Current

Upcoming

Question 9

Which following production process term best describes the situation when activities in a stage of production must stop because there is no work?

Blocking

Buffering

Starving

Buffer

Setup time

Question 10

Which of the following is not considered a major process flow structure?

Work Center

Project

Assembly line

Fabrication

Continuous Flow

Question 11

You are hired as a consultant to decide if your client should purchase a new, highly specialized, piece of equipment. The product to be produced by this equipment is forecast to have a total worldwide demand of 15,000 units over the entire product life. The initial investment to acquire and install the equipment is $256,000. The variable cost to produce each unit will be $15 and the selling price for the finished product will be $30. Which of the following best describes the situation the firm is facing?

The company will recover its initial investment

The company’s total margin will be less than its investment

It’s a good investment

The break-even is lower than the 15,000 units that are expected to sell

All of the above

Question 12

An advantage of a make-to-stock process is which of the following?

Rapid delivery of a standard product

All units of output are unique

It responds directly to customer orders

It allows the firm to avoid inventory costs

It combines the best features of other processes

Question 13

Which of the following is not a benefit of a manufacturing cell layout?

Better human relations

Improved operator expertise

Less in-process inventory and material handling

Faster production setup

Reduced cost

Question 14

A process flowchart uses which of the following symbols to represent storage areas or queues in a flow diagram?

Rectangle

Arrow

Inverted triangle

Diamond

A dashed line

Question 15

Which of the following basic types of production layout formats is one which has similar equipment or functions are grouped together?

Production line layout

Assembly line layout

Workcenter layout

Group technology layout

Manufacturing cell layout

Question 16

A difference between project and continuous flow categories of process flow structures is which of the following?

The size of the product

Discrete parts moving from workstation to workstation

Degree of equipment specialization

Being a “Virtual Factory”

Profit per unit

Question 17

To reduce process throughput time you might try which of the following actions?

Outsource activities

Change the sequence of activities

Improve teamwork

Reduce management interference

Introduce incentive pay

Question 18

Which of the following is a partial measure of productivity?

Output/Materials

Output/(Labor + Capital + Energy)

Output/All resources used

Output/Inputs

All of the above

Question 19

Which of the following terms describes the time a unit spends actually being worked on together with the time spent waiting in a queue?

Cycle time

Flow time

Run time

Setup time

Efficiency

Question 20

Which of the following is not a basic type of process structure?

Product-process matrix

Workcenter

Manufacturing cell

Assembly line

Continuous process

Question 21

According to Little’s law, which of the following can be used to estimate inventory?

Process time/Cycle time

Throughput rate times flow time

Process velocity/flow time

Set up time/Throughput rate

Value added time/Process velocity

Question 22

Assume a fixed cost for a process of $15,000. The variable cost to produce each unit of product is $10 and the selling price for the finished product is $25. Which of the following is the number of units that has to be produced and sold to break-even?

500 units

667 units

790 units

900 units

1,000 units

Question 23

Which of the following is a measure of operations and supply management efficiency used by Wall Street?

Dividend payout ratio

Current ratio

Receivable turnover

Earnings per share growth

Financial leverage

Question 24

Which of the following basic types of process structures is one which equipment or work processes are arranged according to the progressive steps by which the product is made?

Project

Workcenter

Manufacturing cell

Assembly line

Continuous process

Question 25

Which of the following best describes the term cycle time?

Average time between completions of successive units

Ratio of the time a resource is activated over its use

Can be no more that 60 minutes

The same as utilization

The labor content of the item being measured

Question 26

A process flowchart uses which of the following symbols to represent a decision point in a flow diagram?

Rectangle

Arrow

Inverted triangle

Diamond

A dashed line

Question 27

Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?

3

5

6

8

None of the above

Question 28

The ability to rapidly and inexpensively switch production from one product to another enables what are sometimes referred to as:

Economies of scale

Economies of size

Economies of shape

Economies of scope

Economies of shipping

Question 29

According to Little’s Law, which of the following ratios is used to find flow time?

Cycle time/Process time

Throughput time/Process velocity

Process velocity/Throughput time

Inventory/Throughput rate

Value added time/Process velocity

Question 30

Which of the following basic types of process structures is one which similar equipment or functions are grouped together?

Project

Workcenter

Manufacturing cell

Assembly line

Continuous process

Question 31

To reduce process flow time you might try which of the following actions?

Perform activities in parallel

Change the sequence of activities

Reduce interruptions

Acquire additional equipment

All of the above

Question 32

We would expect to see in a manufacturing cell layout which of the following?

Large teams who collectively do a small part of a finished product

A small team of workers who turn out complete units of work

More in-process inventory

Long production setup times

None of the above

Question 33

You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct value for the resulting line’s efficiency?

0.500

0.833

0.973

0.990

None of the above

Question 34

A major competitive dimension that forms a company’s strategic operational competitive position in their strategic planning is which of the following?

Cost or price

Focus

Automation

Straddling

Activity-system mapping

Question 35

Which of the following is a total measure of productivity?

Output/Materials

Output/(Labor + Capital + Energy)

Output/Labor

Output/Inputs

All of the above

Question 36

When balancing an assembly line, which of the following is not a way to reduce the longest task time below the required workstation cycle time?

Upgrade the equipment

Assign a roaming helper to support the line

Split the task between two workstations

Speed up the assembly line transfer mechanism

Use a more skilled worker

Question 37

When a company seeks to match the benefits of a successful position while maintaining its existing position in offering customers a variety of differing services, what is this process called?

Operations capability analysis

Straddling

Order qualifying

Order winning

Inter-functional analysis

Question 38

Formulate and use linear programming to solve the following problem. A firm wants to determine how many units of each of two products (products X and Y) they should produce in order to make the most money. The profit from making a unit of product X is $100 and the profit from making a unit of product Y is $80. Although the firm can readily sell any amount of either product, it is limited by its total labor hours and total machine hours available. The total labor hours per week are 800. Product X takes 4 hours of labor per unit and Product Y takes 2 hours of labor per unit. The total machine hours available are 750 per week. Product X takes 1 machine hour per unit and Product Y takes 5 machine hours per unit. Write the constraints and the objective function for this problem, solve for the best mix of product X and Y, and report the maximum value of the objective function. (model formulation 5+solving 8=13 points)